Page 21 - KBHA BULLETIN 1
P. 21

18


               with  0.75  acres  of  reclamation  behind  it  for  a  working  area.  The  work  on  these  elements

               together with the slipway was completed in 1918.


               The  Main  Breakwater  was  built  of  precast  concrete  blocks,  each  weighing  about  10  tons.

               These blocks were cast in the block-yard at Table Bay and transported through to Kalk Bay
               harbour works direct by rail, where they were unloaded on site by a 12 ton steam crane. The

               blocks were produced totally by hand with a crew of 5 men. This gang stripped and cleaned

               the moulds, hand mixed and placed the concrete in 3 units for one day’s piece work. This
               amounted to over 30 tons of sand, stone, and cement and they were paid 8 shillings total! A

               total of more than 3000 blocks or 30,000 tons of concrete were used in the project.


               The first part of the breakwater at the shore end was built in straight bonded blockwork on

               level  concrete  foundations.  During  excavations  in  this  initial  phase  of  the  work,  they

               uncovered a substantial old building which had been completely buried in sand. This was one
               of the original lime works buildings from which Kalk Bay derived its name.



               As deeper water was reached, construction was changed to sliced blockwork (Fig. 2.5) which
               is more suitable to accommodate continuing changes in level of the sea bed. A team of three

               divers together with their attendants were the main work force employed on the cleaning and

               preparation of the foundations, and the setting out and laying of the blockwork. The blocks
               were loaded onto a light rail laid on top of the completed wall and pushed out to the second

               15 ton crane on the contract which was used by the divers on foundation and block-laying

               operations (Fig. 2.6.)


               The two cranes mentioned above also proved useful during the 1914-18 War when they were

               used to tranship guns, gun mountings, torpedo nets etc. directly from railtrucks brought to the
               new  harbour  works  into  lighters,  which  then  carried  the  equipment  directly  into  Simon’s

               Town Dockyard.
   16   17   18   19   20   21   22   23   24   25   26