Page 24 - Bulletin 1 1997
P. 24

21


               The construction work proved to be hazardous and arduous because it was being carried out

               in  open  sea  conditions  with  no  protection  from  wind,  waves  or  swell.  Over  the  total
               construction period, a total of more than 20% of the time was lost due to unsuitable weather

               conditions.  During  this  period  of  construction,  the  local  fisherman  took  advantage  of  the

               increasing area of sheltered water being provided by the completed section of the wall, and
               there were 16 motorised fishing boats working out of the new harbour, a number of these

               being converted sailing boats.


               While  the  construction  of  the  main  breakwater  progressed,  work  commenced  on  the  fish-

               landing quay. This was a precast block column structure with concrete panels forming the

               wall between columns.  As sections of the quay were completed, the reclamation or filling
               behind  the  wall  progressed  to  provide  the  working  area  and  buildings  for  the  harbour

               operations. At the same time, the slipway was built complete with a timber cradle capable of

               handling a 24 ton vessel.


                     st
               On 21  June 1917, Kalk Bay Harbour was declared a minor port of the Union. Construction
               was completed in 1918 and the harbour operated in this condition for the next 20 years (Fig.
               2.7.)



               In  1937  plans  were  drawn  up  for  a  new  Northern  Mole  to  complete  the  protection of the
               harbour. The first proposal consisted of a curved mole with three jetties made of piled rail

               lines (Fig. 2.8.) However, a straight mole was constructed, with concrete units at the beach

               end founded on existing bed-rock. The remainder of the structure was formed with tipped
               rock rubble. The new jetty built at the south end of this mole was constructed from braced

               timber frames. These new works were completed in 1939 and gave much more protection to

               the  area  behind  the  main  breakwater,  and  provided  additional  mooring  for  the  many  craft
               using this busy little harbour. The total cost of the mole and jetty was £13,650. In 1963 a

               larger  slipway  was  constructed  next  to  the  original  one.  It  is  capable  of  accommodating
               vessels like pelagic trawlers up to 100 tons (minus their nets which weigh up to 20 tons). (P.

               Stacey, pers. comm.)


               The final main phase of construction work in the harbour was the result of a bad storm during

               Easter 1993 when a black south - easter wind brought with it very heavy seas which removed
   19   20   21   22   23   24   25   26   27   28   29